'Metro Flow' project reaches halfway stage on schedule - chiefs confirm South Shields to Pelaw line set to reopen on time
and live on Freeview channel 276
Metro services have been suspended between Pelaw and South Shields since September 2022 to allow for work on the line-dualling project, which bosses say will make services more reliable, allow for increased frequency of service, and open the door to expanding the network to more destinations.
But Nexus, the public body which owns and manages Metro, said the Metro Flow works are going to plan and are on course to be completed by December 4 – when the line between Pelaw and South Shields is due to re-open.
Advertisement
Hide AdAdvertisement
Hide AdA total of 3km of new line has been installed so far, which has included the complete replacement of five track junctions.
More than 4,000 new sleepers have gone in alongside 16,000 tonnes of new ballast. A thousand rail workers are employed on the vast work site which stretches from Gateshead into South Tyneside.
Metro Flow is being carried out during a 12-week major line closure between Pelaw and South Shields.
It is the longest and biggest planned closure on Metro that Nexus has ever undertaken in 42 years of operations.
Advertisement
Hide AdAdvertisement
Hide AdCathy Massarella, Major Project Director at Nexus, said: “The Metro Flow project has reached the halfway point and the works are making great progress.
“Three kilometres of new Metro tracks have been successfully installed already and we remain on course to get the line back open to customers on December 4.
“The works have been intensive. It is the biggest line closure we have ever undertaken. We have seen sections of old track excavated to make room for the new lines.
“In three key areas we are dualling the track by upgrading the adjacent freight line, which will become part of the Metro’s infrastructure.
Advertisement
Hide AdAdvertisement
Hide Ad“We are really grateful to our customers and our lineside neighbours for their patience while we carry out this project, which involves us working right around the clock.
“Metro Flow will allow us to improve reliability on the Metro system, allow for a greater frequency of services in the future when we have our new trains, and offer scope to examine future opportunities to expand the network to other areas that are currently not served by Metro.”
Cllr Tracey Dixon, leader of South Tyneside Council, said: “We are delighted to be on schedule. Having a safe, reliable and sustainable public transport network is crucial for people to get around, whether they are travelling to work, education or for recreation.
“The planned line closure marks a significant step in the Metro Flow project, an investment which will bring long term benefits to the Borough and the wider region.
Advertisement
Hide AdAdvertisement
Hide Ad“Although it does mean there is continued disruption for those who use the Metro to travel to and from South Tyneside, people are assured that once the Metro Flow project is complete, it will make a huge difference with journey times and frequency vastly improved.
“The track dualling will also help to minimise disruption if problems occur while creating scope for expansion of the Metro network in the future.”
A replacement bus service is in operation while Metro trains are suspended. Service 900 calls at all affected stations on the route and the X900 is an express service from South Shields to Heworth.