“Addressing defects” - South Tyneside Council submits new application for town hall clock tower repairs
Access statement says plans would “retain and conserve the historic fabric, appearance and function of the clock tower.”
South Tyneside Council has submitted a new application for essential repairs to its town hall clock and bell tower, as major maintenance works at the historic site continue.


The civic site’s iconic clock tower has been covered in scaffolding for months as part of “essential maintenance” to the Grade II-listed structure.
Now the council has submitted an application for listed building consent for specific repairs to the clock face and bell tower, along with “localised masonry repairs”.


The plans are ‘part-retrospective’ and a heritage and design and access statement said plans would “retain and conserve the historic fabric, appearance and function of the clock tower, while addressing defects that could otherwise lead to continued deterioration and loss of significant historic material”.
Plans seek permission for clock face repairs, which involve the removal of parts for repair and cleaning, the fitting of some new glass sections and more.
The existing clock mechanism was described as “an important element of the heritage significance of the tower ” and planning documents said works intended to “retain the maximum quantity of historic mechanical material”.
Meanwhile, repairs to the clock tower include bell hammers being restored and refitted, along with a new security lock to internal town hall lobby doors.
The application is described as part-retrospective because some elements of the clock and bell repairs were already under way while the full extent of the additional stonework repairs was being established.
Once that scope was confirmed, the additional works were brought together within a single listed building consent application.


The works are continuing, with completion currently expected in March 2027, subject to contractor availability, and the temporary scaffolding structure would be removed afterwards.
A South Tyneside Council spokesperson said: “The initial listed building consent application covered the scaffolding needed to safely access the town hall clock tower so that further investigations could be carried out and the scope of repairs confirmed.
“Now that this work has taken place, a subsequent application has been submitted detailing the repair works required to the clock face and bell tower, as well as localised masonry repairs and other associated works.”
For more information, visit the council’s planning portal website and search for reference 260471.